Redlands City Hall renovation costs draw scrutiny as project reaches 68% completion

City officials say more than $1 million in contingency funding remains available after approval of additional skylight repairs.

Redlands City Hall renovation costs draw scrutiny as project reaches 68% completion
The former Citrus Center at 300 E. State St. is undergoing a $16.8 million renovation to become Redlands' new City Hall. The project is 68% complete, with approximately $1.06 million in contingency funding remaining. (CFR/File Photo)

REDLANDS, Calif. — The Redlands City Council approved nearly $98,000 in additional skylight repairs at the city's future City Hall on Tuesday, Nov. 17, raising questions about whether more unexpected expenses could emerge as construction continues.

Why it matters: The city's project to convert the former Citrus Center into City Hall is expected to cost approximately $16.8 million, excluding the original property purchase. While renovation costs have risen substantially from early estimates, city officials say the latest amendment is covered by previously approved contingency funding and does not increase the overall project budget.

Details: The council unanimously approved a $97,888 amendment to its contract with McKernan Inc., increasing the agreement from $583,105 to $680,993.

The additional work includes replacing skylight glazing and flashing components to address deterioration and prevent water intrusion near the future City Council chambers.

City staff explained that the original plan called for cleaning the existing skylight glass, but further inspection revealed deteriorating materials and organic growth that required more extensive repairs.

Council Member Paul Barich questioned whether the city should anticipate additional expenses as work continues on City Hall and other construction projects.

"I'm constantly asked, how come city estimates something and all of a sudden we're off by twenty, thirty percent every time we do something," he said.

Barich acknowledged that the repairs were necessary but expressed concern about unexpected construction costs.

City officials explained that renovations to existing buildings can uncover problems that were not apparent during initial planning. Staff said the city anticipated those conditions and included a 10% contingency in the construction budget to address unexpected work.

Contingency funding status: The city approved a $1,402,941 contingency as part of the City Hall construction authorization in December 2025.

As of November, $345,483 of that contingency had been approved for spending, representing 24.6% of the total, according to information provided by the city to Community Forward Redlands.

That leaves approximately $1.06 million of the original contingency not yet approved for spending, while the project is 68% complete.

The contingency was established to address unforeseen conditions during the conversion of the office building, which was constructed in the 1980s.

"Our goal is to extend the building's useful life for another 80 years, and the contingency gives us room in the project budget to address conditions we may only discover once construction is under way," the city said in a statement.

City Hall renovation costs: Redlands purchased the former Citrus Center at 300 E. State St. for $16 million in 2021, with plans to consolidate city offices into the downtown building.

In September 2023, the city estimated approximately $11 million in construction and design expenses to convert the property into City Hall.

By December 2025, the council approved approximately $16.1 million in construction contracts and related services, including contingency funding.

In March 2026, the council approved a $745,152 increase to its construction management agreement with Tilden-Coil Constructors, bringing the contract to approximately $2.1 million and increasing the overall project budget to approximately $16.8 million.

The city has also incurred costs associated with relocating existing tenants. In January 2024, the council approved a $1.1 million reimbursement toward improvements at another property to facilitate Citibank's relocation from the future City Hall building.

Great! You’ve successfully signed up.

Welcome back! You've successfully signed in.

You've successfully subscribed to Community Forward Redlands News.

Success! Check your email for magic link to sign-in.

Success! Your billing info has been updated.

Your billing was not updated.